Parking changes at Antioch BART Station for new lot opening next year

Graphics by BART.

850 more stalls; construction to be completed in multiple stages

As we expand parking at Antioch Station, we will also be making some modifications to the existing parking lot and access roads to comply with codes and improve traffic circulation and curbside operations. These modifications include: relocating permit parking, bike lockers, and the passenger loading zone; relocating and increasing ADA and motorcycle parking, designating spaces for future electric vehicle (EV) charging stations, providing a dedicated bus lane, and other access improvements.

Construction of the Antioch Station Parking Expansion Lot Project began on May 21. The project, located just east of and adjacent to the existing lot, includes:

  • Construction of approximately 850 fee parking stalls
  • Dedicated ADA accessible sidewalk to the Antioch Station
  • Lighting
  • Landscaping surrounding the new parking lot

We anticipate the opening of the new parking lot in early 2021.

All parking stalls that are to be removed or closed temporarily for construction will be signed at least 72 hours in advance. Please look out for barricades and signage to guide you around the work areas during this time.

Construction will occur in multiple stages to ensure that ADA parking, permit, and motorcycle stalls remain available at all times. At this time, Stages 1 and 2 are shown below. An update will be provided for Stages 3 and 4 which are anticipated to occur during September.
– Stage 1: Relocate permit parking; relocate and increase motorcycle parking.
– Stage 2: Construct dedicated bus lane (traffic flow during construction will not be significantly impacted); establish new ADA parking and future EV charging stations; motorcycle parking will be temporarily relocated as shown; install new railing to enhance station access.

Please see the maps of work areas for each stage of construction.

We apologize for this inconvenience and appreciate your patience during this construction.

During the current COVID-19 pandemic, some BART projects, including the Antioch Station Parking Expansion Project, have been designated as essential. For this reason, construction activities on the Antioch Station Parking Expansion Project will continue for the time being. BART and Contractors will ensure that workers comply with all CDC guidelines including the social distancing requirement. BART and Contractors will make adjustments as updates to the current situation are provided.


the attachments to this post:


Antioch BART Station Parking Expansion


BART Antioch Station parking improvements Stage 2


BART Antioch Station parking improvements Stage 1


No Comments so far.

Leave a Reply